Build sequence for a new system
1. Before you close on land
If the land isn't bought yet, ask the seller whether a soil evaluation has ever been done. Pull the tract up in the USDA Web Soil Survey. It won't approve anything, but it shows whether you're likely looking at a standard field or something engineered.
2. Soil evaluation and design
An evaluator records the soil where the system would go. A designer then sizes the tank and disposal area for the home's bedroom count and lays out setbacks to the well, property lines, and any water.
3. County permit
Erath County Environmental Health (100 W. Washington, Stephenville) reviews and permits on-site sewage systems in the county. State rules are on TCEQ's OSSF permit page.
4. Installation
Plan for the install after rough grading. Keep concrete trucks, trailers and the pad for a shop off the field area. Compaction ruins a field before it's ever used.
5. Inspection, then backfill
The county inspects the open system. Aerobic units need a maintenance contract from day one.